The project utilizes the roofs of Qianhe Assembly's workshops 1-4 to install photovoltaic panels, with 620Wp mono-crystalline photovoltaic modules, a total DC side capacity of 4756Wp, and an AC side capacity of 4160kW; it uses 2500kVA and 2000kVA pre-assembled booster transformers to step up the electricity to 10kV for grid connection.
Kunlun New Energy will strictly follow construction standards, meticulously design and construct, ensuring the efficient and stable operation of the photovoltaic components, while also planning for later operations and maintenance to ensure the system's long-term efficient operation. Once completed, the project is expected to generate an average of 4.67 million kWh annually, with a total of 116,753 MWh over 25 years. It can save 38,600 tons of standard coal and reduce carbon dioxide emissions by approximately 105,000 tons, achieving significant economic and environmental benefits.